    Project Summary: Beth Eden Church’s 34,000-square-foot facility was experiencing significant foundation movement, resulting in cracked walls and floors, uneven and sloping surfaces, and sticking doors. Pinnacle Foundation Repair installed more than 200 double-walled steel piers to address the affected areas, achieving approximately seven inches of elevation improvement and completing the project in just 15 days.

    Client: Beth Eden Church
    Client Industry: Church / Religious Facility
    Building Size: 34,000 sq. ft.
    Foundation Repair Services:
    Double-Walled Steel Piers

    Problem

    Beth Eden Church was experiencing several clear signs of significant foundation settlement throughout its 34,000-square-foot facility. Cracks had developed in the walls and floors, sections of the flooring had become uneven and sloped, and doors were beginning to stick.

    With the movement raising structural concerns, the church needed a solution capable of supporting the weight of the large building and addressing the settlement as quickly as possible.

    The scale of the project added another layer of complexity. More than 200 pier locations needed to be completed within an accelerated timeline, and the property had large existing builder piers that would need to be disabled as part of the repair process.

    Solution

    To determine the extent of the foundation movement, Pinnacle conducted an elevation survey and worked with a structural engineer to evaluate the building and develop the appropriate repair plan.

    Because of the size and weight of the structure, the team recommended double-walled steel piers with steel caps to provide the necessary support. More than 200 steel piers were installed and driven approximately 23 to 28 feet deep to reach suitable load-bearing strata.

    The Pinnacle team also had to carefully disable the building’s existing builder piers so the structure could be lifted and properly supported by the new pier system. Hydraulic presses were used throughout the installation and lifting process.

    Despite the size and complexity of the project, the repairs were completed in approximately 15 days.

    Outcome

    After the steel pier system was installed and the building was lifted, Pinnacle achieved approximately seven inches of elevation gain, significantly improving the level of the affected areas and providing long-term structural support for the facility.

    A follow-up plumbing test identified plumbing repairs that were needed after the lift, allowing the church to address those issues as the final step in the process.

    The client was very pleased with both the completed work and the communication throughout the project and shared that they would recommend Pinnacle’s services to the church community and surrounding commercial businesses.